Print this page

Chorlton Street NCP, Manchester

PROJECT: Chorlton Street NCP, Manchester

CLIENT: NML

PLANNING SUPERVISOR: Oscar Faber Consulting Ltd

CONTRACT OVERVIEW: Total car park refurbishment to four car decks with ground floor bus station.

SCOPE OF WORKS:

* Concrete repairs to decks and ramps, columns and soffits

* Resin Injection to fractures

* Total redecoration of concrete structure including columns, walls and soffits

* Replacement of defective expansion joints

* Installation of mechanical joints

* Repairs to defective asphalt membrane

* White thermoplastic lining

* New illuminated signage throughout

* Installation of six camera CCTV surveillance system

* Installation of new Armco crash barriers

* Strengthening of existing crash barriers

* Installation of structural steel support frame to bus station soffit

* Total rewire of all decks including lighting, pay-on-entry systems and CCTV

* Construction of customer services center within car park

* Introduction of pay-on-entry and automatic exit/entry barriers

* Introduction of CCTV security system

* Staircase modifications

* External façade cleaning


STATUS: Principal contractor

VALUE: £950k

DURATION: 26 weeks






Car Park Access Control   |   Car Park Barrier Systems   |   Car Park Barriers   |   Car Park Bollards
Car Park Equipment   |   Car Park Gates   |   Car Park Maintenance   |   Car Park Management
Car Park Markings   |   Car Park Signs   |   Car Park Traffic Control   |   Car Park Control
Car Park Controls   |   Car Park DDA   |   Car Park Refurbishment