PROJECT: Newbridge Street NCP, Newcastle
CLIENT: NCP Ltd
PLANNING SUPERVISOR: Hill Cannon
CONTRACT OVERVIEW: Total car park refurbishment
SCOPE OF WORKS:
* Installation of structural steelwork of soffit of car park
* Access was gained by mobile access platforms
* Cheaper plates at basement level were removed
* Various concrete repairs to decks were carried out
* Also beams over entrance and exist ramps were repaired
* All soffits were scarped down
* New fairing coat anti-carbonation coating applied to front façade
STATUS: Principal contractor
VALUE: £64k
DURATION: 8 weeks